Data Centres & AI Compute

Two trans-Pacific cables land at Manado and geothermal power runs at Lahendong: a base for in-country cloud, disaster-recovery and AI capacity, if you secure your own power supply.

+6.57%Growth 2025 (BPS)
0.87Location quotient () · Information & communication (sector)
1/15regencies and cities specialised (LQ > 1)

What you can only do from North Sulawesi

  • Two trans-Pacific cables land here: SEA-US (2017) and Bifrost (2025). Telin calls Manado Indonesia’s second international gateway after Batam

  • Geothermal power at Lahendong (120 MW), with green-energy certificates from PLN

  • More than 2,000 km from Jakarta and Batam, in UTC+8: a separate risk zone for disaster recovery inside Indonesia

Why invest here

Not a province priority in the Investment Book 2024; this is our own assessment.

  • 2028

    The big hubs are full

    Dublin: new data centres unlikely to connect before 2028 (EirGrid, 2022). Amsterdam caps them; Singapore admits capacity only by tender.

  • PP 71/2019

    Data stays in Indonesia

    Public-scope operators store data at home; banks need OJK approval to go abroad; the Personal Data Protection Law applies since October 2024.

  • 20 Tbps

    Pacific cables land here

    SEA-US (since 2017, about 14,500 km) lands at Kauditan; Bifrost (Telin, Meta, Keppel) landed at Manado in February 2025.

  • 120 MW

    Geothermal at Lahendong

    Four 20 MW PLN units and two 20 MW PGE units.

  • 174 MW

    Power is the limit

    Reserve of the Suluttenggo grid in August 2026: a large site needs its own PLN contract or new generation.

  • US$ 100 million

    Phase 1, about 8 MW

    A 100 MW AI hub needs an estimated US$ 1.2 billion of construction (Turner & Townsend, Jakarta, 2026–27).

Read the full assessment with all sources

Not a province priority in the Investment Book 2024; this is our own assessment. Data-centre demand is moving to places that still have power and cables. In January 2022 Dublin’s grid operator EirGrid said new Dublin data centres were unlikely to be connected before 2028. Amsterdam and Haarlemmermeer paused new data centres in July 2019 and now cap them. Singapore stopped new builds from 2019 and now admits capacity only by tender: about 80 MW awarded in July 2023, and at least 200 MW offered in a second call in December 2025. Indonesia keeps data at home. Public-scope electronic-system operators must process and store their data in Indonesia (PP 71/2019, art. 20), banks need approval to place systems abroad (POJK 11/POJK.03/2022, art. 35), and the Personal Data Protection Law (UU 27/2022) has applied in full since October 2024. North Sulawesi has the cables. The SEA-US system (Telin with partners, in service since August 2017, about 14,500 km, 20 Tbps design capacity) lands at Kauditan in North Minahasa and links Manado with Davao, Guam, Hawaii and Los Angeles. Telin also landed the Bifrost cable (with Meta and Keppel) at Manado in February 2025. Power is the limit. The Lahendong geothermal field supplies 120 MW (four 20 MW units and two 20 MW PGE units), but the reserve of the whole Suluttenggo grid was only about 174 MW in August 2026. A large site therefore needs its own supply contract with PLN, or new generation. A phased AI hub of about 100 MW of IT load needs an estimated US$ 1.2 billion of construction at Turner & Townsend’s Jakarta index (US$ 11.96 per watt, 2026–27), before land, grid works, new generation and IT equipment; phase 1 starts from US$ 100 million, about 8 MW.

Request an introduction

Where this sector is strongest

  1. 1Manado City2.61
  2. 2Tomohon City0.83
  3. 3Kotamobagu City0.57
  4. 4Minahasa0.48
  5. 5Bitung City0.44
  6. 6North Minahasa0.44
LQ > 21–20.5–1< 0.5

LQ: Information & communication (sector). Location quotient 2019–2023 average · line = national average (1.0)

Investment map

Investment ideas

  • Carrier-neutral colocation data centre near the Manado cable landing, built in phases from 10 MW with its own PLN supply contract (phase 1 from US$ 100 million)
  • In-country disaster-recovery and cloud campus for Indonesian banks and public-scope operators, far from Jakarta and Batam (phase 1 from US$ 100 million)
  • AI inference and GPU hall sized to a dedicated power-supply agreement, with Lahendong green-energy certificates (phase 1 from US$ 100 million)
  • Interconnection and meet-me facility for carriers, content networks and the eastern Indonesian cable systems, as part of a data-centre campus (phase 1 from US$ 100 million)