Data centres and AI compute in North Sulawesi: the investor dossier

Two trans-Pacific cables land at Manado, geothermal power runs at Lahendong, and Indonesia keeps regulated data at home. This dossier answers the questions a cloud provider, colocation developer or infrastructure fund asks first, with a source for every figure and the weak points stated openly.

2trans-Pacific cables landing at Manado (SEA-US 2017, Bifrost 2025)
120 MWgeothermal power installed at Lahendong
174 MWspare grid capacity in all of Suluttenggo (August 2026)
Rp 996.74per kWh, PLN high-voltage tariff I-4, Q4 2026

Sources: IndoTelko, Apr 2017CNBC Indonesia, 13 Feb 2025PGE, LahendongPLN via Sulut Review, 16 Aug 2026CNBC Indonesia, 4 Nov 2026

Estimated investment to build the AI hub: US$ 1.2 B to 100 MW in phases (construction; US$ 1.7 B – US$ 1.8 B with new generation if needed; tenant IT and GPUs excluded) · Phase 1: from US$ 100 M (about 8.4 MW) (estimate) See the phases

Scorecard

North Sulawesi against Johor, Batam and Singapore

The five questions a hyperscaler site team asks first, side by side. Every cell has a source and a date; where we found no reliable source, the cell says so.

CriterionNorth SulawesiJohorBatamSingapore
Power pricePLN tariff I-4 (high voltage): Rp 996.74 per kWh, Q4 2026 CNBC Indonesia, 4 Nov 2026About 60 sen per kWh, new TNB ultra-high-voltage class (analyst estimate) Light Reading (TNB 2025 tariff)PLN Batam I-4 (above 30 MVA): Rp 968 per kWh off-peak, Rp 1,066 at peak, Q1 2026 PLN Batam tariff, Jan–Mar 2026S$ 0.2859 per kWh, regulated low-voltage tariff, Q4 2026; data-centre contract prices are not public SP Group tariff Q4 2026 (via GetSolar)
Green share of the gridAbout 27% renewable in the North Sulawesi–Gorontalo grid, mostly geothermal (PLN, November 2026) PLN UID Suluttenggo via SulutDaily, 6 Nov 2026Malaysia: 21% low-carbon electricity in 2025 (national; no Johor figure published) Ember: Malaysia, 2025Not published in our sources Natural gas made 93.1% of electricity in 2025; solar and all other sources about 7% EMA: fuel mix for electricity generation
LandTaxable land value (NJOP) in KEK Bitung about Rp 800,000–1,000,000 per m² (April 2026); the zone covers about 534 ha Sulut Review, 3 May 2026Antara, 11 Jun 2026Not published in our sources Not published in our sources Scarce: new capacity only through government calls; the second call gave 200 MW to four operators (August 2026) W.Media, Aug 2026 (DC-CFA2)
Latency to SingaporeNot measured: no public probe in North Sulawesi. Nearest public probes: 71.4 ms from General Santos, Philippines (520 km away); 20.8 ms from Banjarmasin, Indonesia (1,257 km away) RIPE Atlas measurement 30715243RIPE Atlas probe 7611RIPE Atlas probe 7108Not measured: no RIPE Atlas anchor in Johor 1.9 ms from a Batam anchor (Jan 31, 2026 to Feb 7, 2026, its last week online) RIPE Atlas measurement 30715243RIPE Atlas probe 72760.4 ms inside Singapore (reference) RIPE Atlas measurement 30715243RIPE Atlas probe 7092
Moratorium and permitsNo moratorium. KEK Bitung does not yet list data centres; the draft data-centre regulation names Bitung (October 2026) CNBC Indonesia, 23 Oct 2026Kompas, 24 Jun 2026Tighter since November 2025: no new Tier 1 and Tier 2 centres, reclaimed water required New Straits Times, Nov 2025No moratorium found; BP Batam reports more than Rp 120 trillion in nine data-centre projects (2026) BP Batam / Diskan Batam, 2026Selective: winners of the second call must run more than half their capacity on green energy (August 2026) W.Media, Aug 2026 (DC-CFA2)

Values are as published and not like-for-like: regulated tariffs, an analyst estimate and national grid shares. Rupiah and other currencies are not converted here; see the cost comparison below.

Measured latency

Round-trip time (ping) measured by RIPE Atlas, the open internet measurement network. There is no public probe in North Sulawesi, so we show the nearest public probes and say where they are. These are not measurements from Manado.

Singapore
General Santos71.4 ms
Banjarmasin20.8 ms
Batam1.9 ms
Singapore0.4 ms
Tokyo
General Santos112.9 ms
Banjarmasin170.5 ms
Batam86.7 ms
Singapore64.6 ms
Guam
General Santos111.3 ms
Banjarmasin267.2 ms
Batam66.2 ms
Singapore73.1 ms
Los Angeles
General Santos226.6 ms
Banjarmasin158.5 ms
Batam191.4 ms
Singapore178.2 ms

Median of every ping reply over seven days (4 measurements, 5,942 to 7,527 replies per line). Snapshot taken on Nov 14, 2026; probes that went offline show their last week online. Hawaii: no public anchor. A carrier measurement from Manado is still to be done. Sources: RIPE Atlas measurement 30715243RIPE Atlas measurement 39433115RIPE Atlas measurement 28697410RIPE Atlas measurement 25787507

Power stack

The grid that serves North Sulawesi, Gorontalo and Central Sulawesi on 16 August 2026, with Lahendong geothermal on the same scale.

Available capacity, Suluttenggo 991.36 MW
  • Peak demand 817.5 MW
  • Spare 173.9 MW
Lahendong geothermal, installed 120 MW

Rp 996.74 PLN tariff I-4, Q4 2026

Lahendong is part of the available capacity, not on top of it. A campus of tens of megawatts needs new capacity agreed with PLN. PLN via Sulut Review, 16 Aug 2026PGE, LahendongCNBC Indonesia, 4 Nov 2026

Two Pacific cables land here

SEA-US lands at Kauditan, North Minahasa; Bifrost lands at Manado. Lines join the North Sulawesi landing to the other landing points of the same cable. They are schematic, not the route on the seabed.

SEA-USBifrost

Why your next AI capacity belongs in North Sulawesi

North Sulawesi invites a long-term partner to build an AI campus on Indonesia’s Pacific coast: where two trans-Pacific cables come ashore, where geothermal power runs around the clock, and where the province tailors site, power and permits to your roadmap.

  • Connectivity

    Indonesia’s landing point on the Pacific

    SEA-US and Bifrost connect the province directly to Guam, Hawaii and the US west coast, and to Singapore and Jakarta. Submarine Cable Map: SEA-USCNBC Indonesia, 13 Feb 2025

  • Clean, firm power

    Geothermal that runs 24/7

    Lahendong supplies 120 MW today, with 410 MWe of resource at Kotamobagu and 350 MWe at Lahendong: a path to round-the-clock carbon-free goals such as Google’s for 2030. PGE, LahendongKompas, 7 Feb 2024Google: 24/7 carbon-free by 2030

  • Resilience

    A second Indonesian region, far from the first

    About 2,173 km from Jakarta and 2,314 km from Batam: geographic diversity for in-country availability zones and disaster recovery.

  • Data sovereignty

    Capacity inside Indonesia’s rules

    Public-scope systems must keep data in Indonesia and the data-protection law applies in full; data hosting is open to 100% foreign ownership. PP 71/2019 (BPK JDIH)UU 27/2022 (BPK JDIH)Perpres 10/2021 (BPK JDIH)

  • Cost

    Jakarta tariffs, room to grow

    The same PLN industrial tariff as Jakarta (Rp 996.74 per kWh, Q4 2026) and land for a campus that grows to about 100 MW. CNBC Indonesia, 4 Nov 2026

  • Government backing

    Named by Jakarta, prepared by the province

    Bitung was put forward as a data-centre location in June 2026 and is named in the draft data-centre regulation; one provincial counterpart for site, permits and power. Kompas, 24 Jun 2026CNBC Indonesia, 23 Oct 2026

What North Sulawesi offers

  • Two trans-Pacific cables land here (SEA-US 2017, Bifrost 2025): a direct route to Guam, Hawaii, the US West Coast and the Philippines, not via Singapore or Jakarta
  • In-country capacity for data that must stay in Indonesia, in a separate risk zone more than 2,000 km from Jakarta and Batam
  • Geothermal power at Lahendong (120 MW), more units in preparation, and green-energy certificates (REC) from PLN
  • The same national power tariff as Jakarta and Batam, with lower land and wage costs
  • Government interest: Bitung was named as a candidate data-centre location in 2026

Red flags, and how to handle them

A hyperscaler will find these in its first week. We list them first.

Small grid: about 174 MW spare in all of Suluttenggo
Start with a few megawatts, ask PLN for a connection study before buying land, and tie later phases to new geothermal units. PLN via Sulut Review, 16 Aug 2026
Earthquakes, tsunami warnings and active volcanoes
Seismic design to SNI 1726:2019 with a site survey, sites set back from the east coast and on higher ground, and a twin site in another risk zone. Kompas, 2 Apr 2026CNN Indonesia, 18 Apr 2024
Far from the main internet exchanges in Jakarta and Singapore
Use the direct trans-Pacific cables, buy diverse domestic capacity, and help set up a local exchange node.
Hot and humid all year: no free cooling
Liquid cooling for AI racks and efficient chillers. Singapore, with a similar climate, requires a PUE of 1.3 or better. AKCP, 23 Jul 2026 (Singapore roadmap)
No data-centre cluster yet: few specialists and suppliers
Anchor-tenant model, a relocated core team, and training with Sam Ratulangi University and Manado State Polytechnic.
Incentives in flux: the tax holiday is not being extended for now
Model the base case without a tax holiday; treat a holiday or free-zone status as upside. CNBC Indonesia, 5 Nov 2026

Answers to a hyperscaler request for information (RFI)

The questions site-selection teams ask, in their order. Every answer gives its source; where we found no source, we say so and do not estimate.

Power

How much grid capacity is spare?
The whole Suluttenggo system (North Sulawesi, Gorontalo and Central Sulawesi) had 991.36 MW available against an 817.5 MW peak on 16 August 2026: a reserve of about 174 MW. For the North Sulawesi–Gorontalo system alone, PLN reported 639 MW of dependable capacity and a 461 MW peak in August 2025. A campus of tens of megawatts therefore needs new capacity, agreed with PLN before you buy land. PLN via Sulut Review, 16 Aug 2026Antara Manado, Aug 2025
What is planned?
PLN’s electricity plan (RUPTL 2025–2034) projects the North Sulawesi–Gorontalo system to grow from about 580 MW in 2025 to 1,730 MW in 2034. New plants include the Sawangan hydro plant (16.6 MW, 2030) and Kotamobagu geothermal (20 MW in 2031, 60 MW in 2033), plus a link to the South Sulawesi grid. These are plans, not a commitment for your load. Antara Manado, 31 Jul 2025 (RUPTL 2025–2034)
Is there renewable power?
Yes. The Lahendong geothermal field has 120 MW installed. PGE gave PLN the technical documents for Lahendong units 7 and 8 (2 × 20 MW) in December 2025 for a power-purchase evaluation, and agreed the tariff of a 15 MW binary unit with PLN in April 2026. Resource potential is about 350 MWe at Lahendong and about 410 MWe at Kotamobagu (Kompas, 2024). PLN sells renewable-energy certificates (REC) and offers dedicated green supply to data centres. PGE, LahendongWarta Ekonomi, Dec 2025PGE at IIGCE 2026Kompas, 7 Feb 2024CNBC Indonesia, 12 Sep 2024
What does power cost?
PLN tariff I-4 (high voltage, from 30 MVA): Rp 996.74 per kWh. Tariff I-3 (medium voltage, above 200 kVA): Rp 1,114.74 per kWh. Both apply in Q4 2026 and did not change during the year. The tariff is national, so it is the same in Jakarta and Batam. We found no special data-centre tariff; PLN says its rates, including certificates, compete with Malaysia and Singapore. CNBC Indonesia, 4 Nov 2026Bisnis.com, 4 Jul 2025
Can I build my own plant or sign a private power deal?
Not simply. PLN runs the grid and retail supply in North Sulawesi. The energy ministry dropped power wheeling (selling private power to a customer over PLN’s grid) from the renewable-energy bill in 2025. Realistic routes: a PLN supply contract with certificates or dedicated green supply; generation on your own site for your own use, under its own licence; or a partnership with a geothermal developer that sells to PLN. Confirm the route with PLN and the energy ministry. Bisnis.com, 1 Mar 2025
Can I get two independent feeds?
PLN says it can supply data centres from at least two separate substations. Which substations can do this for a given plot is part of the PLN connection study, which we help you request. CNBC Indonesia, 12 Sep 2024

Investor & developer checklist

What infrastructure funds and developers (Blackstone and AirTrunk, KKR and STT GDC, GIP and BlackRock’s AI partnership, Stonepeak and Digital Edge, EdgeConneX, DayOne, Princeton Digital, NTT, BDx, DCI, NeutraDC) have shown they need in their deals, and what North Sulawesi can show today. Most groups publish no fixed thresholds, so the “what they need” column is drawn from their published deals.

RequirementWhat investors need (from their deals)Status in North SulawesiWhat we must deliver
ScalePlatform campuses start at about 100 MW: the Equinix xScale joint venture with GIC and CPP builds campuses above 100 MW; AirTrunk’s first Johor campus is 150 MW; Digital Edge plans 500 MW near Jakarta. Smaller first builds exist: NeutraDC Batam with Singtel is 18 MW.Missing Grid reserve of about 174 MW for the whole region: a first phase of a few MW up to about 20 MW is realistic, 100 MW is not without new plants.A phased plan: phase 1 sized to what PLN can connect, later phases tied to new geothermal units. DCD: Equinix xScale JV, Oct 2024Baxtel: AirTrunk Johor, Jul 2026Investortrust: PLN–Digital Edge 2 × 725 MVAThe Tech Capital: NeutraDCPLN via Sulut Review, 16 Aug 2026
Power certaintyA signed PLN supply agreement before construction: Digital Edge signed with PLN in October 2025 for its Cikarang campus, now 2 × 725 MVA.Missing No data-centre supply agreement or connection study in North Sulawesi yet.A PLN UID Suluttenggo connection study and a memorandum of understanding for a named site. Investortrust: PLN–Digital Edge 2 × 725 MVABisnis.com, 4 Jul 2025
Green powerGoogle aims for 24/7 carbon-free energy by 2030; Microsoft has a 100/100/0 goal for 2030. Lenders give green loans (AirTrunk Johor, Princeton Digital Jakarta).In progress Lahendong geothermal (120 MW) and PLN certificates exist; Lahendong units 7–8 are being evaluated.A written PLN offer for certificates or dedicated geothermal-backed supply. Google: 24/7 carbon-free by 2030GeekWire 2026: Microsoft 100/100/0Baxtel: AirTrunk Johor, Jul 2026DCD: PDG green loanWarta Ekonomi, Dec 2025CNBC Indonesia, 12 Sep 2024
Anchor tenantBuild-to-suit and pre-leases of 10–15 years with a creditworthy tenant before building (industry primers; AirTrunk’s first Johor campus was fully contracted).Missing No anchor tenant yet.An anchor strategy: Telin and carriers, banks’ disaster-recovery sites, public-scope cloud, AI-inference customers in eastern Indonesia and the Philippines. CREFC data-centre primer, 25 Feb 2026Baxtel: AirTrunk Johor, Jul 2026
Land and titleIndustrial-estate land with clear building rights (HGB).In progress KEK Bitung (about 534 ha) has a manager, but data centres are not yet one of its activities; other plots are unverified.A land bank of clean-title plots with data-centre zoning, and a KEK decision to admit data centres. Antara, 11 Jun 2026Kompas, 2023 (KEK Bitung land)Kompas, 24 Jun 2026
ConnectivityDiverse fibre to the main exchanges and cable landings.In progress Two trans-Pacific cables and neuCentrIX are in place; no internet-exchange node and unverified domestic diversity.Carrier offers for two separate routes, and a local exchange node with the carriers. IndoTelko, Apr 2017DCD: Telin Bifrost CLS ManadoTelkom, Jan 2019
Hazard dataSite-specific seismic, tsunami and flood data.Missing Regional data only (BMKG, USGS, InaRISK).A feasibility study with a geotechnical and seismic survey per shortlisted plot. USGS earthquake catalogueBNPB InaRISK
Rules and incentivesClear ownership and data rules; predictable incentives.In progress 100% foreign ownership and data localisation are clear; a draft data-centre regulation names Bitung; the tax holiday is not being extended for now.Follow the draft regulation and the free-zone route; give investors a dated status. Perpres 10/2021 (BPK JDIH)PP 71/2019 (BPK JDIH)CNBC Indonesia, 23 Oct 2026CNBC Indonesia, 5 Nov 2026
Country risk and protectionInvestment-grade sovereign rating and treaty protection.Available S&P BBB stable (July 2026); Moody’s Baa2 and Fitch BBB, both with a negative outlook (February and March 2026). The Indonesia–Singapore investment treaty (in force since March 2021) allows international arbitration.Explain holding structures with legal advisers; this is national, not provincial. The Diplomat, Jul 2026 (S&P)Bank Indonesia, Feb 2026 (Moody’s)KTWB, 4 Mar 2026 (Fitch)UNCTAD: Indonesia–Singapore BIT 2018
CurrencyLong contracts, often priced in US dollars abroad.Missing Domestic transactions must be in rupiah (Currency Law 7/2011, Bank Indonesia rule 17/3/PBI/2015); exemptions are narrow.Legal advice on tariff indexation and offshore contracts. Clifford Chance, May 2015
Returns and exitStabilised data-centre cap rates of about 5.0–7.5% (US, first half 2026); exits through REITs and stake sales (NTT DC REIT in Singapore, July 2025; KKR and Singtel’s purchase of STT GDC, 2026).Missing No operating data centre to value in North Sulawesi.A first project with a bankable tenant, so a track record exists. Houlihan Lokey, Oct 2026Mingtiandi: NTT DC REIT, Jul 2025STT GDC, Sep 2026
Sovereign co-investorLocal partners reduce risk: Indonesia’s sovereign fund INA invested in DayOne’s Batam campus; Danantara plans a data-centre platform.Missing No sovereign co-investor in a North Sulawesi project.An approach to INA and Danantara with a concrete site and power plan. Mingtiandi: INA in DayOneAntara, 2026 (Danantara)

Status as of 13 November 2026. Available = exists and is sourced; In progress = announced, drafted or under evaluation; Missing = not found.

Best locations for data centres and AI compute

Six areas, scored on six criteria from the sourced facts in this dossier. The scores are our own assessment, not a study: a feasibility study per plot comes first.

Map: candidate areas, existing infrastructure and what could be built

Candidate areaExisting infrastructureFree zone (KEK)Possible, to be studied

Positions are approximate area centres, not plots. Orange-ringed points marked “possible, to be studied” are ideas for new infrastructure: none is planned, financed or approved.

AreaPower 25%Connectivity 20%Land 15%Hazards 20%Rules & incentives 10%Access & talent 10%Score (of 100)
Kauditan and Kema cable corridor (North Minahasa)AI or cloud campus (10 MW and more)35433473
Mapanget, Manado (airport area)Colocation (1–10 MW)34333568
KEK Bitung (Tanjung Merah)AI or cloud campus (10 MW and more)33424463
Lahendong and Tomohon (geothermal area)Edge or pilot (under 1 MW)42223354
Kotamobagu (Bolaang Mongondow)Long term31333250
KEK LikupangNot recommended23221344
AI or cloud campus (10 MW and more)Kauditan and Kema cable corridor (North Minahasa)

Next to the SEA-US landing station, between Manado and Bitung: the best connectivity in the province and room for a campus. The east coast receives tsunami warnings, so choose a site set back and on higher ground.

2 km from the SEA-US landing · 27 km from Lahendong · 17 km from the port of Bitung (straight line)

Colocation (1–10 MW)Mapanget, Manado (airport area)

Close to Telkom’s neuCentrIX, the airport, customers and staff: right for colocation, interconnection and a first phase of a few megawatts. Plots are smaller; avoid low land that floods.

26 km from the SEA-US landing · 30 km from Lahendong · 32 km from the port of Bitung (straight line)

AI or cloud campus (10 MW and more)KEK Bitung (Tanjung Merah)

A 534 ha free zone with a manager, close to the port, and named by the government as a candidate data-centre location. It needs the zone to admit data centres, a fibre link to the landing stations and coastal hazard design.

7 km from the SEA-US landing · 35 km from Lahendong · 9 km from the port of Bitung (straight line)

Edge or pilot (under 1 MW)Lahendong and Tomohon (geothermal area)

Next to the 120 MW geothermal field: the strongest green-power story. A volcanic area with hilly land and no cable landing: suited to edge and pilot sites, or as a power source for a campus elsewhere through PLN.

30 km from the SEA-US landing · 1 km from Lahendong · 45 km from the port of Bitung (straight line)

Long termKotamobagu (Bolaang Mongondow)

A large geothermal resource (about 410 MWe) and planned PLN geothermal units (2031 and 2033). Far from the cables and from Manado: a long-term option if new geothermal capacity is built.

111 km from the SEA-US landing · 84 km from Lahendong · 126 km from the port of Bitung (straight line)

Not recommendedKEK Likupang

A tourism free zone (197 ha). Data centres are not among its activities, and the coast serves resorts: not recommended.

34 km from the SEA-US landing · 51 km from Lahendong · 29 km from the port of Bitung (straight line)

Infrastructure that could be built (possible, to be studied)

Possible, to be studiedNew substation with two feeds for a campus

A dedicated high-voltage substation between Kauditan and Bitung with two independent feeds, to be studied with PLN.

Possible, to be studiedGeothermal-backed green supply

A PLN supply contract tied to Lahendong units 7–8 or a new geothermal unit, with certificates.

Possible, to be studiedDiverse fibre ring Kauditan–Bitung–Manado

Two physically separate routes between the landing stations, a campus and neuCentrIX.

Possible, to be studiedCable landing extension to Bitung

A branch or new domestic cable landing at Bitung, which the government called an untapped landing point in June 2026.

Possible, to be studiedNeutral internet exchange in Manado

A node of a national exchange with the carriers, so traffic in eastern Indonesia stays local.

Possible, to be studiedSeawater cooling at Bitung

Seawater heat rejection for a coastal campus, subject to environmental approval.

Costs compared with other data-centre hubs

Published figures only, each with its source. Where North Sulawesi has no published figure, the cell says “to be quoted”.

HubPower price (as published)≈ per kWh, in your currencyBuild cost per MW (T&T 2026–27)Colocation rent per kW per month (CBRE)Sources
North SulawesiPLN I-4 (≥ 30 MVA): Rp 996.74/kWhUS$ 0.055to be quotedto be quotedCNBC Indonesia, 4 Nov 2026
JakartaPLN I-4 (≥ 30 MVA): Rp 996.74/kWhUS$ 0.055US$ 12 Mnot published in our sourcesCNBC Indonesia, 4 Nov 2026EdgeProp, Oct 2026 (T&T 2026–27)
BatamPLN Batam I-4 (> 30 MVA): Rp 968/kWh off-peak, Rp 1,066/kWh peak (Q1 2026); converted at the off-peak rateUS$ 0.053not in the indexnot published in our sourcesPLN Batam tariff, Jan–Mar 2026
Johorabout 60 sen/kWh, new TNB ultra-high-voltage class (analyst estimate) (estimate)–US$ 10.1 Mnot published in our sourcesLight Reading (TNB 2025 tariff)EdgeProp, Oct 2026 (T&T 2026–27)
SingaporeS$ 0.2859/kWh regulated low-tension tariff, Q4 2026 (data-centre contract prices not public)–US$ 15.4 MUS$ 330 – US$ 475SP Group tariff Q4 2026 (via GetSolar)Turner & Townsend APAC, 29 Oct 2026CBRE Global DC Trends 2026, 17 Jun 2026
Northern VirginiaVirginia industrial average 9.98 US cents/kWh, Aug 2026US$ 0.100US$ 11.8 MUS$ 190 – US$ 235US EIA Electric Power Monthly, 23 Oct 2026Turner & Townsend DCCI 2026–27, 22 Oct 2026CBRE Global DC Trends 2026, 17 Jun 2026
Dublin€ 0.2552/kWh, Ireland non-household 500–2,000 MWh band, H2 2025–US$ 12.6 Mnot published in our sourcesEurostat, 8 May 2026Turner & Townsend DCCI 2026–27, 22 Oct 2026
Nordics (build cost: Stockholm)Sweden € 0.0970, Finland € 0.0748/kWh, same Eurostat band, H2 2025–US$ 13.9 Mnot published in our sourcesEurostat, 8 May 2026Turner & Townsend DCCI 2026–27, 22 Oct 2026
Tokyoabout ¥ 28.26/kWh business average, Mar 2026 (negotiated data-centre prices not public)–US$ 18.3 MUS$ 280GlobalPetrolPrices, Mar 2026Turner & Townsend APAC, 29 Oct 2026CBRE Global DC Trends 2026, 17 Jun 2026
Osakaabout ¥ 28.26/kWh business average (national), Mar 2026–US$ 17.2 Mnot published in our sourcesGlobalPetrolPrices, Mar 2026Turner & Townsend APAC, 29 Oct 2026
Manilanot published in our sources–US$ 9.6 Mnot published in our sourcesEdgeProp, Oct 2026 (T&T 2026–27)
Ho Chi Minh CityVND 1,811/kWh normal hours, industry ≥ 110 kV (EVN, May 2025)–US$ 8.3 Mnot published in our sourcesEVN: Decision 1279/QD-BCT, May 2025Turner & Townsend APAC, 29 Oct 2026
  • Power prices are as published and not like-for-like: regulated tariffs, a US state average and EU consumption bands. Large data centres usually negotiate.
  • Build cost is construction only, for a typical 60 MW design; land, grid connection and IT equipment are excluded.
  • Rupiah prices are converted at the site’s current exchange rate; switch currency at the top of the page.
  • North Sulawesi is in no cost index we found; its costs are quoted in a feasibility study.

Investment size: the estimated investment for the AI hub

The question every investor asks first. The hub is built in phases to about 100 MW of IT load. These are indicative construction costs from a published index, not a quote for North Sulawesi; what the index leaves out is listed separately.

Estimated investment to build the AI hub: about US$ 1.2 B to 100 MW in phases, construction only; about US$ 1.7 B – US$ 1.8 B if new geothermal generation is needed. Tenant IT and GPUs are not included. (estimate)

Phase 1: from US$ 100 M (about 8.4 MW) Phase 1 math: US$ 100 M ÷ US$ 11.96 per watt (Jakarta, Turner & Townsend 2026–27) = about 8.4 MW of IT load, construction only; a first hall of 10 MW is about US$ 119.6 M. (estimate)

PhaseIT load, cumulativeGrid supply to ask PLN for (IT load × PUE 1.3–1.54)Construction in this phaseConstruction, cumulative (Jakarta basis)Cumulative, regional span (Johor to Singapore)
Phase 110 MW13–15.4 MWUS$ 119.6 M (estimate)US$ 119.6 MUS$ 100.6 M – US$ 153.9 M
Phase 225 MW32.5–38.5 MWUS$ 179.4 M (estimate)US$ 299 MUS$ 251.5 M – US$ 384.8 M
Phase 350 MW65–77 MWUS$ 299 M (estimate)US$ 598 MUS$ 503 M – US$ 769.5 M
Phase 4100 MW130–154 MWUS$ 598 M (estimate)US$ 1.2 BUS$ 1 B – US$ 1.5 B
  • Method: megawatts of IT load × US$ per watt from the Turner & Townsend Data Centre Construction Cost Index 2026–27 (typical 60 MW design, construction only). Basis: Jakarta, US$ 11.96 per watt, the nearest indexed market. Span: Johor US$ 10.06 to Singapore US$ 15.39 per watt.
  • The index gives no figure for smaller halls; a 10 MW hall can cost more or less per watt.
  • Grid supply adds cooling and losses: PUE 1.3 is Singapore’s target for new data centres, 1.54 the global average (Uptime Institute, 2025).
  • All amounts are estimates, rounded, and shown in your currency at the site’s current rate.

EdgeProp, Oct 2026 (T&T 2026–27)Turner & Townsend APAC, 29 Oct 2026AKCP, 23 Jul 2026 (Singapore roadmap)Uptime Institute survey 2025

Not included in these amounts

Land
Not in the index. NJOP (the tax value, not a market price) in KEK Bitung is about Rp 800,000–1,000,000 per m²; plot size depends on the design. Sulut Review, 3 May 2026
Grid connection and substation
Not in the index, and no published price for Suluttenggo: PLN quotes it after a connection study.
Fibre
Diverse routes to the SEA-US landing at Kauditan and to Bifrost in Manado: to be quoted by the carriers. IndoTelko, Apr 2017CNBC Indonesia, 13 Feb 2025
GPUs and IT equipment
Not in the index, and the largest item for AI. A published reference: Nvidia’s CEO put 1 GW of AI data centre at US$ 50–60 billion, about US$ 35 billion of it Nvidia chips and systems (2025). Per MW that is US$ 50 M – US$ 60 M all-in and about US$ 35 M of Nvidia hardware. It varies with the hardware generation; a cloud or colocation tenant usually brings its own. CNBC, 22 Sep 2025 (Nvidia CEO on cost per gigawatt)
Design fees, permits and contingency
Not in the index; to be quoted in the feasibility study.

What published deals in the region cost

Reference points from announcements, each with its source. Amounts are what was announced: a total investment, a loan, or a multi-year programme without a capacity. US$ per MW is our own division, shown only for a total investment with a capacity.

ProjectCapacityAmountWhat the amount isPer MW (our division)Source
Digital Edge CGK campus, Bekasi–Cikarang (Stonepeak)500 MWUS$ 4.5 Btotal investment: design capacity; PLN supply 2 × 725 MVAUS$ 9 M (estimate)Investortrust: PLN–Digital Edge 2 × 725 MVA
AirTrunk JHB2, Johor (Blackstone)270 MWUS$ 2.3 Bloan or financing: 270 MW and more; green loan, July 2026–Baxtel: AirTrunk Johor, Jul 2026
EdgeConneX, Bekasi (EQT)120 MWUS$ 403.8 Mloan or financing: up to 120 MW; sustainability-linked financing, December 2024–DCD: EdgeConneX Indonesia
Princeton Digital JC2, Jakarta22 MWUS$ 105 Mloan or financing: 22 MW; loan converted to green financing–DCD: PDG green loan
Equinix JK1, Jakarta–US$ 74 Mtotal investment: opened May 2025; capacity not stated–Equinix, 15 May 2025
Microsoft, Indonesia–US$ 1.7 Bmulti-year programme: cloud and AI, 2024–2028–Microsoft, 30 Apr 2024
Amazon Web Services, Jakarta region–US$ 5 Bmulti-year programme: planned over 15 years from 2021–TechNode Global, 14 Dec 2021

A loan or financing covers part of a project, so it is not a cost per MW. Capacities are as announced (design or contracted), not built.

Phase 1: what US$ 100 million builds, three ways

Three ways to spend the first US$ 100 million, worked out from the same published figures. The splits are estimates with the method shown; land, grid connection and fibre are to be quoted and reduce what is left for buildings.

A. Developer campus: powered shell and colocation

For a developer or fund that leases space and power; the tenant brings its own IT and GPUs.

US$ 100 million at the Jakarta index builds about 8.4 MW of IT load, construction only, in a Tier III design. Turner & Townsend’s split of construction cost for an air-cooled data centre (US projects, 2025 index) shows where it goes: (estimate)

Electrical: switchgear, UPS, generators, distribution54% of constructionUS$ 54 M
Mechanical and cooling22% of constructionUS$ 22 M
Shell and architectural14% of constructionUS$ 14 M
Contractor costs10% of constructionUS$ 10 M

On top, to be quoted: land and site preparation, the PLN connection with a two-feed substation, diverse fibre to the SEA-US landing at Kauditan and to Bifrost, security and building management outside the contractor’s scope, design fees and contingency. Each reduces the megawatts US$ 100 million buys.

EdgeProp, Oct 2026 (T&T 2026–27)Turner & Townsend DCCI 2025: cost trends
B. AI-inference cluster: fewer megawatts, GPUs included

For an AI or cloud company that owns its hardware and wants capacity in Indonesia.

One NVIDIA GB200 NVL72 rack draws about 120 kW (NVIDIA) and was estimated at about US$ 3 M (HSBC, 2024; NVIDIA publishes no price). That is about US$ 25 M of hardware per MW of IT load, about twice the building. Building (US$ 12 M per MW) plus racks (US$ 25 M per MW) is about US$ 37 M per MW, so US$ 100 million buys about 2.7 MW, or about 22 racks, before land, grid, fibre, networking and storage. On the all-in figure of Nvidia’s CEO (US$ 50–60 million per MW) it would be 1.7–2 MW. (estimate)

NVIDIA DGX GB rack user guide, Sep 2026Tom’s Hardware, May 2024 (HSBC estimate)CNBC, 22 Sep 2025 (Nvidia CEO on cost per gigawatt)EdgeProp, Oct 2026 (T&T 2026–27)
C. Staged campus: a first hall, infrastructure for 50–100 MW

For a long-term investor who wants room to grow with demand and new geothermal power.

Phase 1 builds a 5 MW hall (US$ 59.8 M construction at the Jakarta index) and leaves about US$ 40.2 M of the US$ 100 million for land for the whole campus, a substation and grid connection sized for later phases, diverse fibre and the studies. Whether that is enough depends on PLN’s connection offer and the land price: the feasibility study answers it. Later halls follow demand. (estimate)

EdgeProp, Oct 2026 (T&T 2026–27)

Our assessment: option C fits North Sulawesi best today, because the grid reserve is limited and there is no anchor tenant yet; option A fits once a tenant signs; option B fits a tenant with its own GPU programme. All amounts are estimates; each card shows its method.

Recommended technical spec for an AI-ready site in North Sulawesi

Liquid-cooling ready
Plan for racks of about 120 kW, the draw of one NVIDIA GB200 NVL72 rack. Turner & Townsend put liquid-cooled builds at about 7–10% above air-cooled (US projects, 2025 index). NVIDIA DGX GB rack user guide, Sep 2026Turner & Townsend DCCI 2025: cost trends
Seismic design
SNI 1726:2019 with a site-specific seismic hazard study (PSHA); base isolation as an option to price.
Siting
On higher ground, outside tsunami and flood hazard zones on InaRISK, set back from the east coast. BNPB InaRISK
Redundancy
A Tier III design (maintainable without shutdown): N+1 cooling and generators, a 2N power path to the racks and two independent grid feeds.
Green power
A PLN supply contract with Lahendong geothermal certificates, or dedicated geothermal-backed supply. PGE, LahendongCNBC Indonesia, 12 Sep 2024
Cooling in a hot, humid climate
Design for a PUE near Singapore’s 1.3 target, with closed-loop liquid cooling to limit water use. AKCP, 23 Jul 2026 (Singapore roadmap)
Build speed
Modular, prefabricated data halls and power skids, so later phases follow demand.

Full build-out: what a 100 MW AI campus needs

The order of magnitude behind a full campus, item by item. Construction and new generation are estimates from published indices; what has no published price is marked “to be quoted”. GPUs and IT equipment are the tenant’s and are not included.

ItemAmountBasis
Construction, 100 MW of IT loadUS$ 1.2 B (estimate)100 MW × US$ 11.96 per watt, Turner & Townsend 2026–27, Jakarta basis, construction only. EdgeProp, Oct 2026 (T&T 2026–27)
New generation, if PLN cannot supply from the gridUS$ 522 M – US$ 618.3 M (estimate)The campus draws 130–154 MW from the grid (PUE 1.3–1.54); the reserve of all of Suluttenggo is about 174 MW. Priced at IRENA’s 2024 global average for new geothermal plants (US$ 4,015 per kW; eight plants, range US$ 1,217 to US$ 6,724 per kW). Whether it is needed, and whether PLN, PGE or an independent producer builds it, is to be studied. IRENA, Renewable Power Generation Costs in 2024PLN via Sulut Review, 16 Aug 2026AKCP, 23 Jul 2026 (Singapore roadmap)Uptime Institute survey 2025
Grid connection, substation, fibre and landto be quotedNo published price for Suluttenggo; PLN, the carriers and the land owner quote them in the feasibility study.
GPUs and IT equipmenttenant-funded, not includedFor reference only: Nvidia’s CEO put an AI data centre at about US$ 35 M of Nvidia hardware per MW (2025). CNBC, 22 Sep 2025 (Nvidia CEO on cost per gigawatt)

Order of magnitude before the items to be quoted: about US$ 1.7 B – US$ 1.8 B (construction plus new generation); construction alone US$ 1.2 B. Estimates, rounded.

Who funds a campus of this size: in the published deals, infrastructure funds and developers put in equity and borrow against signed tenants. Stonepeak has put more than US$ 3 billion of equity into Asia-Pacific data centres (Digital Edge, Princeton Digital); AirTrunk financed its second Johor campus with a US$ 2.3 billion green loan; EdgeConneX raised US$ 403.8 million of financing for its Bekasi campus. Industry primers describe build-to-suit and 10–15-year pre-leases with a creditworthy tenant before building. We publish no debt or equity percentages: they depend on the tenant contract and the lenders. Asia Asset: Stonepeak in Asia-PacificBaxtel: AirTrunk Johor, Jul 2026DCD: EdgeConneX IndonesiaCREFC data-centre primer, 25 Feb 2026

Where the demand is: hyperscalers and developers in Indonesia

Google CloudJakarta cloud region since June 2020. Jakarta Post, 24 Jun 2020
Amazon Web ServicesJakarta region since December 2021, with about US$ 5 billion planned over 15 years. TechNode Global, 14 Dec 2021
MicrosoftIndonesia Central region (West Java, three availability zones) opened in May 2025, part of US$ 1.7 billion for cloud and AI from 2024. Microsoft, 27 May 2025Microsoft, 30 Apr 2024
EquinixJK1 in Jakarta opened in May 2025, about US$ 74 million. Equinix, 15 May 2025
EdgeConneXJakarta (Bekasi) since 2023, with US$ 403.8 million of financing to expand to 120 MW. DCD: EdgeConneX Indonesia
BatamThe Batam authority counts more than Rp 120 trillion of data-centre investment in nine projects (2026). BP Batam / Diskan Batam, 2026
BitungProposed by the government as a new data-centre location (June 2026); named with Kupang in a draft regulation (October 2026). Kompas, 24 Jun 2026CNBC Indonesia, 23 Oct 2026

Investment ideas

Investment idea: a Manado AI hub, about US$ 1.2 B to 100 MW in phases

A phased, AI-ready campus in the Kauditan–Bitung corridor, next to two trans-Pacific cables, with green power through geothermal-backed certificates. Sized to what PLN can connect, not to a headline.

  1. Phase 0: feasibility (3–9 months)

    PLN connection study, plot, seismic and hazard surveys, fibre routes, permits.

  2. Phase 1: 10 MW AI-ready hall

    Inference, cloud and disaster-recovery capacity on a PLN I-4 supply contract with certificates. Indicative construction cost US$ 119.6 M (estimate); the hub starts from US$ 100 million (about 8 MW).

  3. Phase 2: to 25 MW

    Another 15 MW, about US$ 179.4 M (estimate), once PLN confirms the connection and a second substation feed.

  4. Phase 3: to 50 MW

    Another 25 MW, about US$ 299 M (estimate), only with new capacity (Lahendong 7–8, Kotamobagu geothermal or other PLN additions).

  5. Phase 4: to 100 MW

    Another 50 MW, about US$ 598 M (estimate), with new generation (see Full build-out).

The costs are our estimate: megawatts × Turner & Townsend’s index for Jakarta (US$ 11.96 per watt, 2026–27), construction only, without land, grid works, new generation or GPUs. A Manado quote can be higher or lower. Phase 1 starts from US$ 100 million.

Ir. Hermina Syaloom Dailly Korompis, SP., MSc

Ask Hermina about data centres

She answers from this dossier, with sources.

Shared value

Compute that strengthens a region, not only a network

The province seeks a partner whose investment advances the 2030 Agenda for Sustainable Development: clean energy, quality jobs and skills, and digital infrastructure for eastern Indonesia, delivered transparently and together with the communities of North Sulawesi.

SDG 9

Digital infrastructure for the east

Hyperscale capacity, a neutral internet exchange and a diverse fibre ring beyond the Jakarta–Batam corridor. Telkom, Jan 2019

SDG 8

Decent, skilled work

Permanent technical jobs in operations, power and security, with local suppliers in construction and services.

SDG icons are used for information; no UN endorsement is implied. SDGs

Feasibility study: what a bankable site study covers

Lenders and tenants ask for it before land, power contracts or construction. We coordinate the feasibility study with DPMPTSP North Sulawesi, PLN UID Suluttenggo and the KEK Bitung administrator. The study decides whether a site works; we do not promise its outcome.

1Power and grid

Connection study and supply offer from PLN: capacity, voltage, two feeds, timeline, green certificates.

2Ground and seismic

Geotechnical survey and a probabilistic seismic hazard analysis (PSHA) for design to SNI 1726:2019.

3Tsunami and flood

Hazard check on InaRISK and a site-level assessment of inundation and drainage.

4Land and zoning

Title (HGB) check, zoning, and whether KEK Bitung admits data centres.

5Fibre and latency

Route survey and carrier offers for two separate routes; measured latency to Jakarta, Singapore and Guam.

6Climate and cooling

Design basis for temperature and humidity, cooling concept, water source and use.

7Environment

Environmental approval route (AMDAL or UKL-UPL, depending on size).

8Concept design and cost

Concept design and an early-stage (Class 4–5) cost estimate.

9Market and tenants

Demand study and anchor-tenant sounding.

10Financing

Structure, lenders, green-loan eligibility and a sovereign co-investor (INA, Danantara).

  • Duration: about six months, within months 3–9 of the timeline above (our planning estimate).
  • Cost: to be quoted; we found no published reference price.
  • Who does it: international engineering, cost and real-estate advisers (for example the firms that publish data-centre cost indices, such as Turner & Townsend and Cushman & Wakefield) with Indonesian consultants registered for environmental studies and surveys. Named as examples from public sources, not as a recommendation.

Site exclusivity: possible terms

Province-wide or sector-wide exclusivity is not possible: the Investment Law (UU 25/2007, art. 4(2)(a) and art. 6(1)) requires equal treatment of all investors, domestic and foreign. What is common is a reservation of a specific site for a limited time. The terms below are options to negotiate, not an offer. UU 25/2007 (JDIH Kemenkeu)

Scope
One named plot or campus area, not a region or a sector.
Duration
12 to 24 months.
Reservation fee or deposit
Set per site and credited against the land price or lease; amount to be agreed.
Milestones
Month 6: PLN application filed and feasibility study started. Month 12: feasibility study delivered and PLN memorandum of understanding. By month 24: land agreement, anchor tenant or own use, phase-1 financing. Construction start by month 36 becomes a condition of the land agreement.
Lapse
The reservation ends automatically when a milestone is missed.
Commitment
Tied to a phase-1 investment plan of at least US$ 100 million.
Right of first refusal
Optionally, on adjoining land for later phases, for the same period.

Every term needs legal review and agreement with DPMPTSP North Sulawesi and, inside a free zone, the KEK administrator and the land owner.

In or near a free zone (KEK)

A free zone (KEK) gives the strongest incentives, but only for the zone’s main activities. Our assessment of the route for data centres, with its status.

KEK Bitung today
Set up by PP 32/2014 for industry, logistics and export processing. Data centres are not one of its main activities, so the 100% corporate-tax reduction in a KEK, which applies to main activities (PMK 237/2020), is not available to them now; a business outside the main activities only gets the investment-type income-tax facility. Antara, 11 Jun 2026PMK 237/2020 (KEK tax facilities)
Route 1: add data centres as a main activity
PP 40/2021 lists research, digital economy and technology development among KEK activities (art. 9) and lets the National KEK Council set each zone’s main activities (art. 72). The KEK administrator and the province would propose it to the Council. Precedent: KEK Nongsa in Batam was set up as a digital zone (PP 68/2021). Status: not proposed yet. PP 40/2021, art. 9PP 40/2021, art. 72
Route 2: a digital sub-zone along the cable corridor
Extending KEK Bitung towards the Kauditan–Bitung cable corridor means amending its government regulation: a longer route, to be studied with the National KEK Council.
Fallback: national incentives outside a KEK
The tax holiday’s pioneer-industry list includes the digital economy limited to data processing, hosting and related activities (PMK 130/2020 as amended by PMK 69/2024), but the government said in November 2026 that the tax holiday will not be extended for now. Whether the exact KBLI codes qualify for the tax allowance (PP 78/2019) we did not verify: to be checked in its annex. DDTC: digital economy in the tax holidayCNBC Indonesia, 5 Nov 2026
KEK Likupang
A tourism zone; not recommended for data centres.

Our recommendation: two tracks at once. Ask the KEK administrator and the National KEK Council to add data centres to KEK Bitung, and plan the base case on national rules without a tax holiday, so the project does not depend on either. Status 13 November 2026: neither track has started.

H.E. Guido Lassally

Your contact for the AI hub

H.E. Guido Lassally

Deputy Business Ambassador of North Sulawesi · Invest North Sulawesi

Talk to us in confidence about your requirements: megawatts, timing, power profile and latency. We arrange the site visit with DPMPTSP and PLN.

+31 6 1683 8463 WhatsApp

guido@northsulawesi.org

Our assessment from public sources, status 13 November 2026. Not legal, tax, engineering or investment advice. Scores and estimates are labelled as such; nothing on this page is a commitment by PLN, the government or any operator.