North Sulawesi AI Hub: an AI campus at Indonesia’s Pacific gateway
A phased AI and cloud campus beside two trans-Pacific cable landings, powered by geothermal energy: Phase 1 from US$ 100 million, growing to about 100 MW of IT load.
Status: In preparation with PLN and DPMPTSP · expressions of interest welcome
Deal sheet
- Ticket size
- Phase 1 from US$ 100 million; estimated total about US$ 1.7–1.8 billion in phases to about 100 MW, excluding tenant IT and GPUs
- Stage
- Idea · Step 1 of 5Site and power in preparation; feasibility study next
- Land
- Candidate sitesKauditan cable corridor, Mapanget (Manado) or KEK Bitung; no permitted plot yet.
- Location
- North Minahasa, Manado City, Bitung City
- Source
- Data-centre investor dossier, northsulawesi.org/data-centres (13 November 2026)
- Turner & Townsend Data Centre Construction Cost Index 2026–27
- IRENA Renewable Power Generation Costs in 2024
- PLN UID Suluttenggo system figures (August 2026)
Every value comes from the project’s own documents, listed under Sources. Where those documents do not give a value, we show “Not yet known” instead of an estimate.
The challenge
Indonesia requires public-scope systems to keep their data in the country, and demand for cloud and AI capacity keeps growing. Hyperscalers need a second Indonesian region with its own cable route, clean power and room to grow, far from the existing hubs around Jakarta and Batam. North Sulawesi has the cables and geothermal power, but no data-centre site with a signed power supply yet.
The approach
- 1Site
A named plot in the Kauditan cable corridor, Mapanget (Manado) or KEK Bitung, reserved for 12–24 months with milestones.
- 2Power
A PLN connection study and supply agreement for Phase 1, with renewable certificates; new geothermal capacity for the later phases.
- 3Campus
Phase 1 of about 8–10 MW of IT load, growing to 25, 50 and about 100 MW as demand and power allow.
- 4Partnership
A transparent selection in two stages (expression of interest, then proposals), issued by the Provincial Government or the KEK administrator.
Timeline
- NowSite and power preparation with DPMPTSP and PLN; expressions of interest welcome
- Months 0–9Feasibility study: power, ground and seismic hazard, land and title, fibre, design and cost
- Months 12–36Phase 1 construction after the land and power agreements
- 2030sPhases 2 to 4 with new geothermal capacity, as PLN confirms it
Investment summary
- Structure
- Developer or hyperscaler campus on a reserved site; own use or leased capacity; co-investment by infrastructure funds or sovereign investors possible
- Use of funds
- Data halls, electrical and cooling plant, substation and grid connection, fibre and land; new geothermal supply in the later phases
How to take part
- Book a confidential call about your requirements: megawatts, timing, power profile and latency.
- Read the investor dossier on data centres and AI compute, with a source for every figure.
- Visit the Kauditan corridor, Mapanget and KEK Bitung with DPMPTSP and PLN.
- Take part in the selection when the Provincial Government issues it.
Partners
- Provincial Government of North Sulawesi through DPMPTSP: issuer of the selection and one-stop licensing
- PLN UID Suluttenggo: grid connection and supply
- KEK Bitung administrator: sites inside the zone
- Invest North Sulawesi: preparation and facilitation