Provinsi Sulawesi Utara · Indonesia
Invest North Sulawesi
← Back to the dossier
Invest North Sulawesinorthsulawesi.org · Provinsi Sulawesi Utara · Indonesia

Investor dossier · data centres & AI compute

North Sulawesi data centres & AI compute: investor brief

Two trans-Pacific cables land at Manado, geothermal power runs at Lahendong, and Indonesia keeps regulated data at home. This dossier answers the questions a cloud provider, colocation developer or infrastructure fund asks first, with a source for every figure and the weak points stated openly.

2trans-Pacific cables landing at Manado (SEA-US 2017, Bifrost 2025)
120 MWgeothermal power installed at Lahendong
174 MWspare grid capacity in all of Suluttenggo (August 2026)
Rp 996.74per kWh, PLN high-voltage tariff I-4, Q4 2026

Estimated investment to build the AI hub: about US$ 1.2 B to 100 MW in phases, construction only; about US$ 1.7 B–1.8 B if new geothermal generation is needed. Tenant IT and GPUs are not included. (estimate)

What North Sulawesi offers

  • Two trans-Pacific cables land here (SEA-US 2017, Bifrost 2025): a direct route to Guam, Hawaii, the US West Coast and the Philippines, not via Singapore or Jakarta
  • In-country capacity for data that must stay in Indonesia, in a separate risk zone more than 2,000 km from Jakarta and Batam
  • Geothermal power at Lahendong (120 MW), more units in preparation, and green-energy certificates (REC) from PLN
  • The same national power tariff as Jakarta and Batam, with lower land and wage costs
  • Government interest: Bitung was named as a candidate data-centre location in 2026

Red flags, and how to handle them

  • Small grid: about 174 MW spare in all of Suluttenggo. Start with a few megawatts, ask PLN for a connection study before buying land, and tie later phases to new geothermal units.
  • Earthquakes, tsunami warnings and active volcanoes. Seismic design to SNI 1726:2019 with a site survey, sites set back from the east coast and on higher ground, and a twin site in another risk zone.
  • Far from the main internet exchanges in Jakarta and Singapore. Use the direct trans-Pacific cables, buy diverse domestic capacity, and help set up a local exchange node.
  • Hot and humid all year: no free cooling. Liquid cooling for AI racks and efficient chillers. Singapore, with a similar climate, requires a PUE of 1.3 or better.
  • No data-centre cluster yet: few specialists and suppliers. Anchor-tenant model, a relocated core team, and training with Sam Ratulangi University and Manado State Polytechnic.
  • Incentives in flux: the tax holiday is not being extended for now. Model the base case without a tax holiday; treat a holiday or free-zone status as upside.

Best locations for data centres and AI compute

  1. Kauditan and Kema cable corridor (North Minahasa) · 73/100 · AI or cloud campus (10 MW and more)
  2. Mapanget, Manado (airport area) · 68/100 · Colocation (1–10 MW)
  3. KEK Bitung (Tanjung Merah) · 63/100 · AI or cloud campus (10 MW and more)
  4. Lahendong and Tomohon (geothermal area) · 54/100 · Edge or pilot (under 1 MW)
  5. Kotamobagu (Bolaang Mongondow) · 50/100 · Long term
  6. KEK Likupang · 44/100 · Not recommended

Six areas, scored on six criteria from the sourced facts in this dossier. The scores are our own assessment, not a study: a feasibility study per plot comes first.

Investment idea: a Manado AI hub, about US$ 1.2 B to 100 MW in phases

A phased, AI-ready campus in the Kauditan–Bitung corridor, next to two trans-Pacific cables, with green power through geothermal-backed certificates. Sized to what PLN can connect, not to a headline.

Phase 1: from US$ 100 million (about 8.4 MW)

PhaseIT load, cumulativeConstruction in this phaseConstruction, cumulative (Jakarta basis) (estimate)
Phase 110 MWUS$ 119.6 MUS$ 119.6 M
Phase 225 MWUS$ 179.4 MUS$ 299 M
Phase 350 MWUS$ 299 MUS$ 598 M
Phase 4100 MWUS$ 598 MUS$ 1.2 B

The RFI in one line each

Power
174 MW spare in Suluttenggo (Aug 2026); Lahendong geothermal 120 MW; PLN I-4 Rp 996.74/kWh (Q4 2026); supply through PLN, power wheeling not available.
Connectivity
SEA-US (Kauditan, 2017) and Bifrost (Manado, 2025); neuCentrIX Manado; no internet-exchange node yet.
Land & sites
KEK Bitung (534 ha) named as a candidate data-centre location; NJOP about Rp 0.8–1 million per m².
Hazards
Active seismic and volcanic region; tsunami warnings in 2026; design to SNI 1726:2019.
Climate
About 25–26 °C and humid all year: design for a PUE near Singapore’s 1.3 target.
Rules
100% foreign ownership for hosting; data localisation for public-scope operators; tax holiday not being extended for now.
Costs
Build cost to be quoted (Jakarta US$ 11.96 per watt); same power tariff as Jakarta and Batam.
Feasibility
Bankable site study (PLN, seismic, hazards, title and KEK, fibre, design and cost, tenants, financing), about six months; we coordinate it.
Full build-out
100 MW: about US$ 1.2 billion construction, plus about US$ 0.5–0.6 billion if new geothermal generation is needed (IRENA 2024); grid, land, fibre to be quoted; GPUs tenant-funded.
Site terms
No regional exclusivity (UU 25/2007); a 12–24-month site reservation with milestones. KEK: ask to add data centres to KEK Bitung; plan on national rules.
Talent
UNSRAT and Manado State Polytechnic; specialists to be relocated.

Costs compared with other data-centre hubs

HubPower price (as published)Build cost per MW (T&T 2026–27)
North SulawesiPLN I-4 (≥ 30 MVA): Rp 996.74/kWhto be quoted
JakartaPLN I-4 (≥ 30 MVA): Rp 996.74/kWhUS$ 12 M
BatamPLN Batam I-4 (> 30 MVA): Rp 968/kWh off-peak, Rp 1,066/kWh peak (Q1 2026); converted at the off-peak ratenot in the index
Johorabout 60 sen/kWh, new TNB ultra-high-voltage class (analyst estimate)US$ 10.1 M
SingaporeS$ 0.2859/kWh regulated low-tension tariff, Q4 2026 (data-centre contract prices not public)US$ 15.4 M
Northern VirginiaVirginia industrial average 9.98 US cents/kWh, Aug 2026US$ 11.8 M
Dublin€ 0.2552/kWh, Ireland non-household 500–2,000 MWh band, H2 2025US$ 12.6 M
Nordics (build cost: Stockholm)Sweden € 0.0970, Finland € 0.0748/kWh, same Eurostat band, H2 2025US$ 13.9 M
Tokyoabout ¥ 28.26/kWh business average, Mar 2026 (negotiated data-centre prices not public)US$ 18.3 M
Osakaabout ¥ 28.26/kWh business average (national), Mar 2026US$ 17.2 M
Manilanot published in our sourcesUS$ 9.6 M
Ho Chi Minh CityVND 1,811/kWh normal hours, industry ≥ 110 kV (EVN, May 2025)US$ 8.3 M

Build cost is construction only, for a typical 60 MW design; land, grid connection and IT equipment are excluded.

Investor & developer checklist

  • Missing Scale: A phased plan: phase 1 sized to what PLN can connect, later phases tied to new geothermal units.
  • Missing Power certainty: A PLN UID Suluttenggo connection study and a memorandum of understanding for a named site.
  • In progress Green power: A written PLN offer for certificates or dedicated geothermal-backed supply.
  • Missing Anchor tenant: An anchor strategy: Telin and carriers, banks’ disaster-recovery sites, public-scope cloud, AI-inference customers in eastern Indonesia and the Philippines.
  • In progress Land and title: A land bank of clean-title plots with data-centre zoning, and a KEK decision to admit data centres.
  • In progress Connectivity: Carrier offers for two separate routes, and a local exchange node with the carriers.
  • Missing Hazard data: A feasibility study with a geotechnical and seismic survey per shortlisted plot.
  • In progress Rules and incentives: Follow the draft regulation and the free-zone route; give investors a dated status.
  • Available Country risk and protection: Explain holding structures with legal advisers; this is national, not provincial.
  • Missing Currency: Legal advice on tariff indexation and offshore contracts.
  • Missing Returns and exit: A first project with a bankable tenant, so a track record exists.
  • Missing Sovereign co-investor: An approach to INA and Danantara with a concrete site and power plan.

Phase 1: what US$ 100 million builds, three ways

A. Developer campus: about 8.4 MW of IT load, construction only; the tenant brings IT and GPUs (estimate). B. AI-inference cluster: about 2.7 MW including about 22 GPU racks (estimate). C. Staged campus: a 5 MW hall (US$ 59.8 M), about US$ 40.2 M left for land, substation, fibre and studies (estimate).