Investor dossier · data centres & AI compute
North Sulawesi data centres & AI compute: investor brief
Two trans-Pacific cables land at Manado, geothermal power runs at Lahendong, and Indonesia keeps regulated data at home. This dossier answers the questions a cloud provider, colocation developer or infrastructure fund asks first, with a source for every figure and the weak points stated openly.
Estimated investment to build the AI hub: about US$ 1.2 B to 100 MW in phases, construction only; about US$ 1.7 B–1.8 B if new geothermal generation is needed. Tenant IT and GPUs are not included. (estimate)
What North Sulawesi offers
- Two trans-Pacific cables land here (SEA-US 2017, Bifrost 2025): a direct route to Guam, Hawaii, the US West Coast and the Philippines, not via Singapore or Jakarta
- In-country capacity for data that must stay in Indonesia, in a separate risk zone more than 2,000 km from Jakarta and Batam
- Geothermal power at Lahendong (120 MW), more units in preparation, and green-energy certificates (REC) from PLN
- The same national power tariff as Jakarta and Batam, with lower land and wage costs
- Government interest: Bitung was named as a candidate data-centre location in 2026
Red flags, and how to handle them
- Small grid: about 174 MW spare in all of Suluttenggo. Start with a few megawatts, ask PLN for a connection study before buying land, and tie later phases to new geothermal units.
- Earthquakes, tsunami warnings and active volcanoes. Seismic design to SNI 1726:2019 with a site survey, sites set back from the east coast and on higher ground, and a twin site in another risk zone.
- Far from the main internet exchanges in Jakarta and Singapore. Use the direct trans-Pacific cables, buy diverse domestic capacity, and help set up a local exchange node.
- Hot and humid all year: no free cooling. Liquid cooling for AI racks and efficient chillers. Singapore, with a similar climate, requires a PUE of 1.3 or better.
- No data-centre cluster yet: few specialists and suppliers. Anchor-tenant model, a relocated core team, and training with Sam Ratulangi University and Manado State Polytechnic.
- Incentives in flux: the tax holiday is not being extended for now. Model the base case without a tax holiday; treat a holiday or free-zone status as upside.
Best locations for data centres and AI compute
- Kauditan and Kema cable corridor (North Minahasa) · 73/100 · AI or cloud campus (10 MW and more)
- Mapanget, Manado (airport area) · 68/100 · Colocation (1–10 MW)
- KEK Bitung (Tanjung Merah) · 63/100 · AI or cloud campus (10 MW and more)
- Lahendong and Tomohon (geothermal area) · 54/100 · Edge or pilot (under 1 MW)
- Kotamobagu (Bolaang Mongondow) · 50/100 · Long term
- KEK Likupang · 44/100 · Not recommended
Six areas, scored on six criteria from the sourced facts in this dossier. The scores are our own assessment, not a study: a feasibility study per plot comes first.
Investment idea: a Manado AI hub, about US$ 1.2 B to 100 MW in phases
A phased, AI-ready campus in the Kauditan–Bitung corridor, next to two trans-Pacific cables, with green power through geothermal-backed certificates. Sized to what PLN can connect, not to a headline.
Phase 1: from US$ 100 million (about 8.4 MW)
| Phase | IT load, cumulative | Construction in this phase | Construction, cumulative (Jakarta basis) (estimate) |
|---|---|---|---|
| Phase 1 | 10 MW | US$ 119.6 M | US$ 119.6 M |
| Phase 2 | 25 MW | US$ 179.4 M | US$ 299 M |
| Phase 3 | 50 MW | US$ 299 M | US$ 598 M |
| Phase 4 | 100 MW | US$ 598 M | US$ 1.2 B |
The RFI in one line each
- Power
- 174 MW spare in Suluttenggo (Aug 2026); Lahendong geothermal 120 MW; PLN I-4 Rp 996.74/kWh (Q4 2026); supply through PLN, power wheeling not available.
- Connectivity
- SEA-US (Kauditan, 2017) and Bifrost (Manado, 2025); neuCentrIX Manado; no internet-exchange node yet.
- Land & sites
- KEK Bitung (534 ha) named as a candidate data-centre location; NJOP about Rp 0.8–1 million per m².
- Hazards
- Active seismic and volcanic region; tsunami warnings in 2026; design to SNI 1726:2019.
- Climate
- About 25–26 °C and humid all year: design for a PUE near Singapore’s 1.3 target.
- Rules
- 100% foreign ownership for hosting; data localisation for public-scope operators; tax holiday not being extended for now.
- Costs
- Build cost to be quoted (Jakarta US$ 11.96 per watt); same power tariff as Jakarta and Batam.
- Feasibility
- Bankable site study (PLN, seismic, hazards, title and KEK, fibre, design and cost, tenants, financing), about six months; we coordinate it.
- Full build-out
- 100 MW: about US$ 1.2 billion construction, plus about US$ 0.5–0.6 billion if new geothermal generation is needed (IRENA 2024); grid, land, fibre to be quoted; GPUs tenant-funded.
- Site terms
- No regional exclusivity (UU 25/2007); a 12–24-month site reservation with milestones. KEK: ask to add data centres to KEK Bitung; plan on national rules.
- Talent
- UNSRAT and Manado State Polytechnic; specialists to be relocated.
Costs compared with other data-centre hubs
| Hub | Power price (as published) | Build cost per MW (T&T 2026–27) |
|---|---|---|
| North Sulawesi | PLN I-4 (≥ 30 MVA): Rp 996.74/kWh | to be quoted |
| Jakarta | PLN I-4 (≥ 30 MVA): Rp 996.74/kWh | US$ 12 M |
| Batam | PLN Batam I-4 (> 30 MVA): Rp 968/kWh off-peak, Rp 1,066/kWh peak (Q1 2026); converted at the off-peak rate | not in the index |
| Johor | about 60 sen/kWh, new TNB ultra-high-voltage class (analyst estimate) | US$ 10.1 M |
| Singapore | S$ 0.2859/kWh regulated low-tension tariff, Q4 2026 (data-centre contract prices not public) | US$ 15.4 M |
| Northern Virginia | Virginia industrial average 9.98 US cents/kWh, Aug 2026 | US$ 11.8 M |
| Dublin | € 0.2552/kWh, Ireland non-household 500–2,000 MWh band, H2 2025 | US$ 12.6 M |
| Nordics (build cost: Stockholm) | Sweden € 0.0970, Finland € 0.0748/kWh, same Eurostat band, H2 2025 | US$ 13.9 M |
| Tokyo | about ¥ 28.26/kWh business average, Mar 2026 (negotiated data-centre prices not public) | US$ 18.3 M |
| Osaka | about ¥ 28.26/kWh business average (national), Mar 2026 | US$ 17.2 M |
| Manila | not published in our sources | US$ 9.6 M |
| Ho Chi Minh City | VND 1,811/kWh normal hours, industry ≥ 110 kV (EVN, May 2025) | US$ 8.3 M |
Build cost is construction only, for a typical 60 MW design; land, grid connection and IT equipment are excluded.
Investor & developer checklist
- Missing Scale: A phased plan: phase 1 sized to what PLN can connect, later phases tied to new geothermal units.
- Missing Power certainty: A PLN UID Suluttenggo connection study and a memorandum of understanding for a named site.
- In progress Green power: A written PLN offer for certificates or dedicated geothermal-backed supply.
- Missing Anchor tenant: An anchor strategy: Telin and carriers, banks’ disaster-recovery sites, public-scope cloud, AI-inference customers in eastern Indonesia and the Philippines.
- In progress Land and title: A land bank of clean-title plots with data-centre zoning, and a KEK decision to admit data centres.
- In progress Connectivity: Carrier offers for two separate routes, and a local exchange node with the carriers.
- Missing Hazard data: A feasibility study with a geotechnical and seismic survey per shortlisted plot.
- In progress Rules and incentives: Follow the draft regulation and the free-zone route; give investors a dated status.
- Available Country risk and protection: Explain holding structures with legal advisers; this is national, not provincial.
- Missing Currency: Legal advice on tariff indexation and offshore contracts.
- Missing Returns and exit: A first project with a bankable tenant, so a track record exists.
- Missing Sovereign co-investor: An approach to INA and Danantara with a concrete site and power plan.
Phase 1: what US$ 100 million builds, three ways
A. Developer campus: about 8.4 MW of IT load, construction only; the tenant brings IT and GPUs (estimate). B. AI-inference cluster: about 2.7 MW including about 22 GPU racks (estimate). C. Staged campus: a 5 MW hall (US$ 59.8 M), about US$ 40.2 M left for land, substation, fibre and studies (estimate).